Both substations feed in parallel. Demand exceeded the capacity of station 2 to supply demand and it tripped the cutout. Only rural connections are radial. Electrical utility starts at the point of demarcation to the generators that make the power.
Both substations feed in parallel. Demand exceeded the capacity of station 2 to supply demand and it tripped the cutout. Only rural connections are radial. Electrical utility starts at the point of demarcation to the generators that make the power.